Much of the talk surrounding the Great Bend Municipal Airport now is centered on Great Bend Airfest which will bring over 30 historic aircrafts to town September 28 – 30.

Airport Manager Martin Miller realizes another large project will take place following the show that will affect the longevity of the runway. Miller says the bidding process for the repaving project on Runway 17/35 is over and now the City of Great Bend is waiting on approval from the Federal Aviation Administration. The total project will cost over $11 million. The FAA agreed to pay 90 percent of the reconstruction for 5,500 feet.

(Read more: Great Bend Post)