After approving the term sheet and site plan for the Soldier Creek Wind Farm in August 2019, the Nemaha County Commissioners announced Monday, Jan. 13 — following a 1-1/2 hour executive session — that they have finalized the haul route for the project.

The commissioners – Tim Burdiek, Gary Scoby and Dennis Henry – have been in negotiations with NextEra Energy Resources, through the county’s hired wind farm attorney James Neeld, on the definitive agreements since the term sheet and site were approved last year. While the haul route has been finalized, the road use agreement is still being negotiated.

Burdiek said township officials met with the commissioners on Friday, Jan. 10, at the Pioneer Building in Seneca. The township officials received maps of the haul route for their township. Burdiek said he encouraged the township officials to drive the roads.