The first phase of Panther Stadium renovations was presented to the USD 260 school board on Monday, July 8. The schematic designs were unveiled for discussion with the board, putting July 22 as the approval date to move forward to the next phase of the project.

The schedule provided by McCownGordon Construction gave an estimated start date of Monday, Dec. 2, 2019. The stadium renovations would be completed by Friday, August 28, 2020, and the start of the 2020-21 school year.

Current USD 260 estimates for the Panther Stadium project sit at $6,545,193. That includes the addition of $129,856 in owner contingency funds.