Evergy has called off plans to run new, taller power poles through Riverside Park and nearby north-central Wichita neighborhoods after two years of vocal opposition from residents. The transmission replacement between the 17th and Emporia substation and the 11th and Jefferson substation will move forward, but the rebuild route will stop there instead of continuing across the river and through the park. “After further evaluation of the transmission line between the substation at 11th Street and Jefferson to the substation at 777 West Central Avenue, we determined the rebuild is not needed at this time,” Evergy Communications Manager Kaley Bohlen said in an email statement. “Infrastructure upgrades we have made throughout the city, as well as a planned substation upgrade (at Third and Mead), have allowed us to remove the project from the current schedule.” She said the existing transmission line connecting the two substations, which was built in the 1950s, will remain in place and continue to serve the area.
Source: Local News | Wichita Eagle