Pottawatomie County commissioners received a less than favorable status update Monday to its ongoing radio systems upgrade, that could see delays well into next year. Motorola representative Richard Nita told commissioners about supply chain delays for the shipment of generators, which had previously been noted to be around 52-weeks. He says their distributor now expects those to be available by the middle of next summer, at best. It was also noted that shelters for the three tower sites are on a 16-week wait, however Topeka-based TFM Comm, whom Motorola is contracted with, had not placed the order as of Monday.
Source: 1350 KMAN