The Manhattan City Commission decided in September 2019 that the building was unsafe and gave the owners until December 2019 to clean it up. Ryan Courtright, Assistant Chief of Risk Reduction with Manhattan Fire Department, said there was damage from the flood and things left over from the previous tenants.
“We actually had a couple of restaurants that were in the building that food product ended up basically being dispersed through out the building and creating an unsanitary condition,” Courtright said.
Courtright said the city will take bids for the demolition starting in mid February, and the city commission will most likely accept a bid at the beginning of March. The company will then have 30 days to start demolition and seven days to finish the demolition.